As part of the ongoing Street Improvements Project, Payne & Dolan, Inc. will begin milling on Wednesday, Sept. 27. Paving will begin on Saturday, Sept. 30. Initial milling work is slated to begin on Genesee Street and asphalt paving is to start on Baraga Avenue. All work is scheduled to take place under flag control or temporary closure to through traffic. The following is a sequence of the planned schedule and the approximate dates for milling & paving.
Milling:
Wednesday, Sept. 27
Genesee (Division to Altamont) and Altamont (US-41 Overpass to McMillan and Genesee to Mesnard)
Thursday, Sept. 28
Longyear (Center to Wright) and Front (Hewitt to Crescent)
Friday, Sept. 29
Baraga (Third to Fifth)
Saturday, Sept. 30
Front (Ridge to Washington and Spring to Fisher)
Asphalt Paving:
Saturday, Sept. 30
Baraga (Third to Fifth)
Front (Ridge to Washington and Spring to Fisher)
Monday, Oct. 2
Jefferson, Sherman, Hancock, Sheridan – First course
Harrison (4th to 6th) – First course
Front (Hewitt to Crescent)
Genesee (Division to Altamont)
Altamont (US-41 Overpass to McMillan and Genesee to Mesnard)
Tuesday, Oct. 3
Genesee (Division to Altamont)
Longyear (Center to Wright)
Wednesday, Oct. 4
Jefferson, Sherman, Hancock, Sheridan – Surface Course
Harrison (Fourth to Sixth) – Surface Course
The above dates are approximate and due to weather and other circumstances, milling and paving may move a day or so earlier or later. Please also adhere to the temporary No Parking signs that will precede the milling and paving. As always please follow all traffic and detour signing.
The City of Marquette asks you for your patience during the construction process.